This Road was taken up at an estimated cost of Rs. 48.95 Crores. The total length of the road is 9.34 Kms. with a ROW of 36Mts with 4-lane divided carriageway with central median of 10.0 Mts wide for a length of 4.00 Kms and 4-lane carriageway with a central median of 2.0 Mts wide for a length of 5.34 Kms.
The Road work is completed and opened to traffic in December, 2011. The total expenditure incurred on this Road is Rs.47.75 Crores.
This Road was taken up with an estimated cost of Rs. 51.54 crores. The length of the road is 7.743 Kms with 4- lane divided carriageway (including Link Road of 843 Mts). The road work for a length of 7.423 Kms is completed and opened to traffic. The balance length of 280 Mts road work in 2 pockets in Sy.no. 145 of Mailardevpally (V) and Sy.no. 67/2 of Jalpally (v) could not be taken up due to land litigation.